At the end of 2023, the progress of the work was already over 60% and the new airport is expected to be inaugurated at the end of 2024. The completed infrastructure also includes a new control tower, a second runway and the new passenger terminal and new commercial area
At the end of 2023, the progress of the works has passed 60% and it is projected that the new airport will be inaugurated at the end of 2024. Among the completed infrastructure is a new control tower and a second landing strip. The new single passenger terminal and the new commercial area are under construction.
Along with the expansion of the Jorge Chavez, the construction of the new Callao Logistics Park is also being carried out, which will meet the growing demand for warehouses in the area with world standards. The work has an area of 96,000 square meters, it is being carried out in 4 phases, the first is already underway, and is expected to be completed in 2026.
The investment in the expansion of Jorge Chavez Airport has attracted new capital from third parties totalling more than 300 million dollars, such as the Callao Logistics Park, a new fuel plant, 3 and 5-star hotels, a new loading zone, new Parking spaces and much more.
According to Project Director Bill Fullerton, together with the Port of Callao and the new Mega Port of Chancay, it is expected that the Jorge Chávez Airport can become the most important logistics center in South America, satisfying the new demand generated.
Date: January 26, 2024